This website provides updates on School District No. 43's (Coquitlam) capital projects including new school construction, seismic replacements projects, additions, and other small projects.
Updates will be posted to each project page linked in the menu to the left, and may include text, photos, videos and applicable links to other websites.
Enquiries may be directed to information@sd43.bc.ca.
Approved Projects
A project is considered approved when it receives Ministry of Education and Child Care funding.
Burke Mountain Secondary
| New School
| Foundational concrete pours and footings are nearing completion. Shear walls are approaching full height, with steel erection set to begin in April. Shotcrete work on secant pile walls is scheduled to start at the end of March or early April, and work on the internal roadway will commence in April (March 2025).
| Fall 2026
|
Centennial Secondary
| Seismic Replacement
| Project complete (November 2024)
| Fall 2024
|
Coast Salish Elementary
| New School
| Childcare facilities complete (November 2024)
| Fall 2024
|
École Dr. Charles Best Secondary
| Addition
| The design of the 12-classroom prefabricated addition is completed. The construction of the addition is expected to begin in the next few weeks (March 2025).
| Fall 2025
|
École Montgomery Middle
| Seismic Replacement
| The new school design process and preliminary planning underway (March 2025)
| Fall 2028
|
Moody Elementary
| Seismic Replacement
| The new Moody Elementary roofing, sheathing, window installation, interior wall erection, electrical wiring and mechanical equipment installation are all underway (March 2025).
| Fall 2025
|
Scott Creek Middle
| Addition
| Occupancy achieved, and addition opened to students in February. Final deficiency remediation and site clean-up is in progress (March 2025).
| Opened 2025
|
*For a variety of reasons, planned completion dates can be revised and will be updated here if they are.