This website provides updates on School District No. 43's (Coquitlam) capital projects including new school construction, seismic replacements projects, additions, and other small projects.
Updates will be posted to each project page linked in the menu to the left, and may include text, photos, videos and applicable links to other websites.
Enquiries may be directed to information@sd43.bc.ca.
Approved Projects
A project is considered approved when it receives Ministry of Education and Child Care funding.
Burke Mountain Secondary
| New School
| Foundational concrete pours and footings are in process (November 2024)
| Fall 2026
|
Centennial Secondary
| Seismic Replacement
| Project complete (November 2024)
| Fall 2024
|
Coast Salish Elementary
| New School
| Childcare facilities complete (November 2024)
| Fall 2024
|
École Dr. Charles Best Secondary
| Addition
| The contract has been awarded to NY Construction Ltd and design work in underway. The move of the two west portables will be completed for the second school term (November 2024).
| Fall 2025
|
École Montgomery Middle
| Seismic Replacement
| Station One Architects awarded contract. Preliminary school design process beginning (November 2024)
| Fall 2028
|
Moody Elementary
| Seismic Replacement
| Structural steel installation nearing completion. Roofing, sheathing, window installation, interior wall erection, electrical wiring and mechanical equipment installation are underway. Preparation for future parking lot underway (November 2024).
| Spring 2025
|
Scott Creek Middle
| Addition
| Roofing and glazing now complete. Breezeway connection to existing school is in progress. Interior fixtures and finishing in progress (November 2024).
| Fall 2024
|
*For a variety of reasons, planned completion dates can be revised and will be updated here if they are.