Four classroom addition opened (Fall 2021)
Letter to the community re: Panorama Heights Addition (April 2021)
Dear Members of the Panorama Heights Elementary Community,
The four classroom addition to Panorama Heights is on schedule to be completed during the summer of 2021 and ready for classes in September 2021. The main structural frame is complete and work is proceeding on the steel stud framing, mechanical and electrical rough-in, and the roof assembly. Over the next couple of months the application of exterior finishes and installation of windows and doors will complete the building envelope. This work will be closely followed by the interior finishing, commissioning of equipment, and exterior ground works. We will continue to keep you updated as construction progresses.
Construction of classroom addition is underway (ongoing)
Letter to Families and Neighbours - Panorama Heights (August 2020)
Panorama Heights Addition - Information Package (June 2020)
Permitting Stage (January 2020)
Design Stage (July 2019)
Ministry funding and approval was received (May 2019)
Project Development Report submitted to Ministry
of Education. Awaiting Ministry funding and approval (June 2018)
SD43 Board of Education commits funds for the addition design. (February 2018)