This webpage provides information and updates on the École Dr. Charles Best Secondary School addition project located in Coquitlam.
The contract has been awarded to NY Construction Ltd and design work in underway. The move of the two west portables will be completed for the second school term (November 2024).
Tender for the 12 classroom addition due on September 13, Design for the 12 additional classrooms will begin soon (September 2024).
Design for the 12 additional classrooms will begin soon (June 2024)
Construction of 6 Classroom Addition complete (February 2021)
Construction of 6 Classroom Addition (Ongoing)
Under construction (April 2020)
Design Stage (July 2019)
Project Development Report submitted to Ministry of Education. Awaiting Ministry funding and approval (June 2018)
SD43 Board of Education is funding the addition project (February 2018)