This website provides updates on School District No. 43's (Coquitlam) capital projects including new school construction, seismic replacements projects, additions, and other small projects.
Updates will be posted to each project page linked in the menu to the left, and may include text, photos, videos and applicable links to other websites.
Enquiries may be directed to information@sd43.bc.ca.
Approved Projects
A project is considered approved when it receives Ministry of Education and Child Care funding.
Burke Mountain Secondary
| New School
| Steel is being erected and infrastructure works underground for the internal roadway and at intersections and David Avenue and Soball Avenue have begun (June 2025).
| Fall 2026
|
Coast Salish Elementary
| New School
| Childcare facilities complete (November 2024)
| Fall 2024
|
École Dr. Charles Best Secondary
| Addition
| The construction of the addition has begun and the excavation and foundational framing is underway and sediment control measures are in place (June 2025).
| Fall 2025
|
École Montgomery Middle
| Seismic Replacement
| The new school design process and advanced planning underway (June 2025)
| Fall 2028
|
Moody Elementary
| Seismic Replacement
| The building envelope is nearing completion and work is well underway in the interior spaces. The contractor is continuing working on the hardscape (June 2025).
| Fall 2025
|
Scott Creek Middle
| Addition
| Occupancy achieved, and addition opened to students in February. Final deficiency remediation and site clean-up is in progress (March 2025).
| Opened 2025
|
*For a variety of reasons, planned completion dates can be revised and will be updated here if they are.